Rescheduled - Equinix Data Centre - Manchester - Power Feed Maintenance - Day Two
Completed
Scheduled for September 14, 2025 at 6:00 AM – 8:00 PM
Affects
Connectivity
Under maintenance from 6:00 AM to 8:00 PM
Core Network
Under maintenance from 6:00 AM to 8:00 PM
Other Services
Under maintenance from 6:00 AM to 8:00 PM
Other
Under maintenance from 6:00 AM to 8:00 PM
Updates
Planned
September 14, 2025 at 6:00 AM
Planned
September 14, 2025 at 6:00 AM
Equinix and their approved contractor will be migrating rack cabinet power supplies to a new Power Distribution Unit within the MA1 Williams House data centre.
Elements of the migration work will reduce cabinet power redundancy to a single power feed for short periods.
On day two (14th September), the B (secondary) feed to each cabinet will be powered down, unplugged, connected to the new supply, and then powered up. Once this has been confirmed, we will move to the next cabinet.
The maintenance window begins at 7 am, with power feed work set to commence from 8 am.
Checks will be made throughout to prevent any disruption, and only one cabinet will be worked on at a time.
RECOMMENDED ACTION: Customers are requested to ensure all their colocated equipment is dual power-fed and the power feeds are not overloaded. We strongly recommend performing your own site visit to visually verify that all equipment is dual-fed.
OUTAGE DURATION: Up to 30 minutes per power feed move.